Prepare for the Florida Building Code Exam. Study with our interactive quizzes featuring multiple choice questions and detailed explanations. Gain confidence in your ability to succeed in this crucial exam!

Each practice test/flash card set has 50 randomly selected questions from a bank of over 500. You'll get a new set of questions each time!

Practice this question and more.


When must a water supply for fire protection be made available on a construction site?

  1. As soon as combustible material accumulates

  2. Before footings are poured

  3. Within 30 days of the Notice of Commencement

  4. After all plumbing has been tested

The correct answer is: As soon as combustible material accumulates

The requirement for a water supply for fire protection on a construction site is crucial for ensuring safety, especially as the work progresses and the risk of fire increases due to the presence of combustible materials. Having firefighting capabilities available as soon as combustible materials accumulate helps mitigate potential fire hazards, safeguarding workers and the site. This reflects a proactive approach to fire safety, aligning with the principles outlined in the Florida Building Code that emphasize preparedness and risk management on construction sites. Therefore, the correct answer underscores the importance of promptly establishing fire protection measures as construction activities begin to elevate the risk factors involved.